Data Center · Emerging Hyperscale Market · Conventional · 2026

    Hyperscale Build-to-Suit Data Center Feasibility Study: Credit Lease

    Build-to-suit single-tenant hyperscale facility pre-leased to an investment-grade tenant: long-term triple-net lease economics, the development spread, and credit-lease underwriting.


    Engagement Snapshot

    MarketEmerging hyperscale market
    Asset typeBuild-to-suit single-tenant hyperscale data center
    FinancingConstruction-to-perm or project finance, or sale-leaseback, conventional and institutional
    Project scale~200 MW of critical IT load, pre-leased on a long-term triple-net lease
    Total project costApproximately $2.26 billion (representative)
    Study scopePower and capacity analysis, credit-lease economics, development cost, yield-on-cost, DSCR and debt yield, valuation, IRR, risk assessment
    Standard of preparationPrepared under USPAP discipline where appraisal is involved

    Representative engagement profile. Project parameters are illustrative of this market. Market figures reflect current third-party data and are sourced in the exhibit below.

    The question put to the analysis

    A developer proposed to build a purpose-built single-tenant hyperscale data center of roughly 200 megawatts of critical IT load, pre-leased to an investment-grade cloud and technology tenant on a long-term triple-net lease, financed through construction-to-permanent or project finance or a sale-leaseback. The lender needed an independent assessment of a fundamentally different question than a speculative multi-tenant build poses: not whether the market would absorb the space, since it was already leased, but whether the power could be delivered, whether the development earned a yield wide enough over the stabilized cap rate, and how the single-tenant credit-lease risk profile compared to the lease-up risk of a colocation development.

    A build-to-suit hyperscale facility is a credit-lease asset, and the feasibility question reflects that. The cash flow is contractual, set by a long-term lease to an investment-grade tenant, so the analysis turns on the durability of that credit, the term and escalations of the lease, and the residual value at expiry, rather than on absorption. The economics are still judged on the development spread, the yield on cost against the cap rate the leased asset would trade at, but the cap rate is tighter and the risk is concentration and renewal rather than lease-up. This engagement profile illustrates how a feasibility study resolves the power question, models long-term triple-net credit-lease economics, judges the development on yield, and frames the single-tenant credit risk against the multi-tenant alternative.

    Power and capacity

    The analysis began with power, the binding constraint regardless of whether the asset is leased.

    Power and capacityFigure
    Critical IT load200 MW
    Assumed PUE~1.18
    Total facility power (IT load x PUE)~236 MW utility demand
    Lease basiscritical IT load on a long-term triple-net lease

    The total utility demand was sized from the IT load and a power usage effectiveness of roughly 1.18, the efficient figure a purpose-built hyperscale facility achieves, producing approximately 236 megawatts of total facility power the utility must deliver. At 200 megawatts, the interconnection is itself a major undertaking, and the analysis treated the utility commitment and the energization schedule as the threshold condition, the same as in a colocation build but at a far larger scale. The difference is that a hyperscale tenant typically co-develops or commits around the power solution, so the power question and the lease are intertwined: the tenant will not sign without a credible power path, and the lender will not fund without the lease.

    The credit lease and the revenue

    Revenue in a build-to-suit is contractual, and the analysis modeled the lease economics directly.

    Lease and revenueFigure
    Contracted revenue (illustrative)~$5 billion over ~15 years
    Average annual contracted revenue~$333 million
    Per-MW basis~$1.67 million per MW per year
    Equivalent per-kW basis~$139 per kW per month
    Lease structureabsolute triple-net, ~2% annual escalations

    The revenue was set by the lease, not the market: a representative contracted total on the order of $5 billion over a roughly 15-year term, averaging approximately $333 million a year, which on the 200-megawatt load works out to roughly $1.67 million per megawatt per year or about $139 per kilowatt per month inclusive of escalations and pass-throughs. Under an absolute triple-net structure, the tenant bears the taxes, insurance, maintenance, and power, so the landlord's net operating income is close to the contracted rent with minimal cost leakage, and the roughly 2 percent annual escalations build the cash flow over the term. The analysis modeled the cash flow as contractual and durable, contingent on the tenant's credit rather than on occupancy.

    Development cost, value, and the yield-on-cost test

    The development was judged on yield-on-cost against the credit-lease cap rate.

    Yield and valueFigure
    Build-to-suit shell-and-core cost (~$11.3M/MW x 200)~$2.26 billion
    Tenant AI fit-out (borne by hyperscaler)up to ~$25M/MW, tenant-funded
    Stabilized NOI (absolute NNN)~$300 million
    Exit cap rate (hyperscale credit)~5.75%
    Implied value (NOI / cap)~$5.2 billion
    Yield-on-cost (NOI / cost)~13.3%

    The landlord's cost was the shell and core at roughly $11.3 million per megawatt, or about $2.26 billion, with the expensive AI fit-out borne by the hyperscale tenant rather than the developer, a key feature of the build-to-suit structure. The stabilized net operating income near $300 million, capitalized at a hyperscale credit cap rate around 5.75 percent, implied a value near $5.2 billion, while the yield on the landlord's cost came to roughly 13.3 percent. The gap between that yield-on-cost and the credit cap rate is a very wide development spread, and it is the entire economic rationale for build-to-suit development: the developer builds at a yield far above the rate the stabilized, credit-leased asset trades at, capturing the spread as value creation.

    Financing and credit-lease underwriting

    The credit was underwritten on the tenant and the lease, not on lease-up.

    FinancingFigure
    Permanent financing55% to 70% LTV, 10 to 25-year terms
    Underwriting basistenant credit rating and lease term
    Takeout optionssale-leaseback, ABS, or CMBS
    Benchmark coverage (hyperscale ABS)DSCR ~1.32x, LTV ~66%

    The financing for a stabilized single-tenant hyperscale asset can approach corporate-bond pricing, because the cash flow is effectively the tenant's credit, and the analysis modeled permanent leverage in the 55 to 70 percent range over a long term, with sale-leaseback, asset-backed securitization, or CMBS as takeout options. The underwriting hinges on the tenant's rating, the lease term, and the residual-value support rather than on occupancy or absorption. The analysis benchmarked the coverage against recent hyperscale securitizations, where debt service coverage near 1.32 times and loan-to-value near 66 percent are representative, and noted that rating agencies stress the renewal probability at lease expiry and assign little or no terminal building value, which is the crux of the credit-lease risk.

    The risk contrast: single-tenant credit versus multi-tenant lease-up

    The analysis framed the risk profile explicitly against the colocation alternative, because the two are mirror images.

    Risk dimensionHyperscale build-to-suitMulti-tenant colocation
    Primary risksingle-tenant credit concentration and renewallease-up and absorption
    Cash flowcontractual, bond-likemarket, with mark-to-market upside
    Cap ratetighter (credit)wider
    Underwriting basistenant credit and lease termpre-leasing and absorption

    The contrast is the analytical heart of the case. The hyperscale build-to-suit removes lease-up risk entirely, replacing it with single-tenant credit-concentration and renewal risk: the cash flow is bond-like and durable while the lease runs, but the asset depends on one tenant and on that tenant renewing at expiry, with rating agencies assigning no terminal building value. The multi-tenant colocation asset carries the opposite profile, lease-up and absorption risk in exchange for diversification and mark-to-market rent upside on renewals. Neither is strictly safer; they are different risks, and the analysis made the trade explicit so the lender could weigh the investment-grade durability of the credit lease against its concentration, rather than treating the leased asset as simply lower-risk.

    Where the risk concentrates

    The risks in a hyperscale build-to-suit are specific and the analysis addressed each. Single-tenant credit concentration is the foremost, because the entire cash flow depends on one tenant, addressed by anchoring the underwriting to an investment-grade rating and the lease term and by distinguishing a true investment-grade hyperscaler from a lower-rated neocloud tenant, which carries materially different risk. Renewal and obsolescence risk attaches to the lease expiry, since the asset depends on the tenant renewing and rating agencies assign no terminal building value, flagged as the central long-term exposure. Power availability and interconnection at 200 megawatts is the threshold condition, intertwined with the tenant's commitment.

    Construction cost and timeline overruns are a capital risk, though the tenant-funded fit-out reduces the developer's exposure. Lease-structure risk, where a short initial term combined with a residual-value guarantee can understate the true obligation, is a subtlety the analysis flagged. Equipment lead times, power cost and sustainability, water use, and interest-rate sensitivity round out the set, with environmental and site due diligence handled as separate scopes.

    Conclusion

    The engagement reached a conditional affirmative, with the conditions tied to power and credit. The 200-megawatt power solution was the threshold condition, intertwined with the tenant's commitment, and the total facility power was sized explicitly from the load and the efficient PUE. The cash flow was modeled as contractual and durable, set by the long-term triple-net lease to an investment-grade tenant, and the development was judged on the very wide spread between the yield on the landlord's cost and the credit cap rate the leased asset would trade at.

    The value of the feasibility study in a build-to-suit is to test the durability of the credit and the width of the development spread, and to frame the single-tenant risk honestly. By sizing the power requirement, by modeling the triple-net credit-lease economics the way the asset actually earns, by judging the development on yield-on-cost against the credit cap rate, and by making the concentration-versus-lease-up trade explicit against the colocation alternative, the analysis gave the lender a clear view of both the bond-like durability of the cash flow and the concentration and renewal risk that define it.

    Market Data Exhibit

    MetricValueNote / Source
    Critical IT load200 MWRepresentative
    PUE / total facility power~1.18 / ~236 MWRepresentative
    Contracted revenue~$5 billion over ~15 yearsRepresentative (cf. recent hyperscale leases)
    Average annual contracted revenue~$333 million (~$139 per kW per month)Representative
    Lease structureabsolute NNN, ~2% escalationsRepresentative
    Build-to-suit shell cost~$11.3 million/MW (~$2.26B total)JLL benchmark
    Stabilized NOI~$300 millionRepresentative
    Exit cap rate~5.75% (hyperscale credit)Industry
    Implied value~$5.2 billionRepresentative
    Yield-on-cost~13.3%Representative
    Permanent financing55% to 70% LTVIndustry
    Benchmark DSCR / LTV (hyperscale ABS)~1.32x / ~66%Recent securitizations

    Pro forma figures are representative of this market. Industry benchmarks are indicative; verify current power availability, lease terms, tenant credit, development costs, cap rates, and financing terms before citation in a client deliverable.